Skip to main content
Feb 26, 2016 / Haseeb Jamal -

5 Travel Myths You Need to Stop Believing Right Now

Feb 26, 2016 / Haseeb Jamal -

Canal Comes Alive with Lighted Boat Parade.

Reinforcement Detailing in Concrete Structures

By: Haseeb Jamal / On: Jul 09, 2017 / Reinforced Concrete
Reinforcement Detailing in Concrete
 
 

Detailing is as important as design since proper detailing of engineering designs is an essential link in the planning and engineering process as some of the most devastating connections. ACI Reinforcement location in non prismatic beam. ACI reinforcement detailing in cantilever beam.

ACI Reinforcement location in non prismatic beam

  • A design engineer's responsibility should include assuring the structural safety of the design, details, checking shop drawing.
  • Detailing is as important as design since proper detailing of engineering designs is an essential link in the planning and engineering process as some of the most devastating collapses in history have been caused by defective connections or DETAILING. There are many examples explained in the book "DESIGN AND CONSTRUCTION FAILURES" by Dov Kaminetzky.
  • Detailing is very important not only for the proper execution of the structures but for the safety of the structures.
  • Detailing is necessary not only for the steel structures but also for the RCC members as it is the translation of all the mathematical expression's and equation's results.
  • For the RCC members for most commonly used for buildings we can divide the detailing for
    • slabs-with or without openings.(rectangular,circular,non-rectangular-pyramid slab,triangular etc)
    • balcony slab, loft slab, corner slab etc
    • beams- with or without openings.(shallow & deep beams)
    • columns. (rectangular, l-shape, t-shape, circular, octagonal, cross shape etc)

Foundations

  • Detailing for gravity loads is different from the lateral loads specially for the SEISMIC FORCES.
  • Apart from the detailing for the above there is a different detailing required for the rehabilitation and strengthening of damaged structures.
  • We will now dwell on the DETAILING OF MEMBERS FOR THE GRAVITY AND SOME DETAILINGS according to the code
  • AS PER IS CODE IS 13920 AND IS 4326 AS REQUIRED FOR SEISMIC FORCES.

Do's & Do Not's for Reinforcement detailing:

Do's General:

  1. Prepare drawings properly & accurately if possible label each bar and show its shape for clarity.
  2. Cross section of retaining wall which collapsed immediately after placing of soil backfill because ¼" rather than 1-1/4" diameter were used. Error occurred because Correct rebar dia. was covered by a dimension line.
  3. Prepare bar-bending schedule , if necessary.
  4. Indicate proper cover-clear cover, nominal cover or effective cover to reinforcement.
  5. Decide detailed location of opening/hole and supply adequate details for reinforcements around the openings.
  6. Use commonly available size of bars and spirals. For a single structural member the number of different sizes of bars shall be kept minimum.
  7. The grade of the steel shall be clearly stated in the drawing.
  8. Deformed bars need not have hooks at their ends.
  9. Show enlarged details at corners, intersections of walls, beams and column joint and at similar situations.
  10. Congestion of bars should be avoided at points where members intersect and make certain that all rein. Can be properly placed.
  11. In the case of bundled bars, lapped splice of bundled bars shall be made by splicing one bar at a time; such individual splices within the bundle shall be staggered.
  12. Make sure that hooked and bent up bars can be placed and have adequate concrete protection.

Indicate all expansion, construction and contraction joints on plans and provide details for such joints. The location of construction joints shall be at the point of minimum shear approximately at mid or near the mid points. It shall be formed vertically and not in a sloped manner.

DO'S - BEAMS & SLABS:

  1. Where splices are provided in bars, they shall be , as far as possible, away from the sections of maximum stresses and shall be staggered.
  2. Were the depth of beams exceeds 750 mm in case of beams without torsion and 450mm with torsion provide face rein. as per IS456-2000.
  3. Deflection in slabs/beams may be reduced by providing compression reinforcement.
  4. Only closed stirrups shall be used for transverse rein. For members subjected to torsion and for members likely to be subjected to reversal of stresses as in Seismic forces.
  5. To accommodate bottom bars, it is good practice to make secondary beams shallower than main beams, at least by 50mm.

Do's - COLUMNS

  1. A reinforced column shall have at least six bars of longitudinal reinforcement for using in transverse helical reinforcement.-for CIRCULAR sections.
  2. A min four bars one at each corner of the column in the case of rectangular sections.
  3. Keep outer dimensions of column constant, as far as possible , for reuse of forms.
  4. Preferably avoid use of 2 grades of vertical bars in the same element.

DO NOT'S - GENERAL

  1. Reinforcement shall not extend across an expansion joint and the break between the sections shall be complete.
  2. Flexural reinforcement preferably shall not be terminated in a tension zone.
  3. Bars larger than 36mm dia. Shall not be bundled.
  4. Lap splices shall be not be used for bars larger than 36mm dia. Except where welded.
  5. Where dowels are provided, their diameter shall not exceed the diameter of the column bars by more than 3mm.
  6. Where bent up bars are provided, their contribution towards shear resistance shall not be more than 50% of the total shear to be resisted.
  7. USE OF SINGEL BENT UP BARS(CRANKED) ARE NOt ALLOWED IN THE CASE OF EARTHQUAKE RESISTANCE STRUCTURES.

DETAILING OF SLABS WITHOUT ANY CUT OR OPENINGS

  • The building plan DX-3 shows the slabs in different levels for the purpose of eliminating the inflow of rainwater into the room from the open terrace and also the sunken slab for toilet in first floor.
  • The building plan DX-A3 is one in which the client asked the architect to provide opening all round.
  • Different shapes of slabs used in the buildings Minimum and max. reinforcement % in beams, slabs and columns as per code provisions should be followed.

SLABS

  1. It is better to provide a max spacing of 200 mm(8") for main bars and 250mm(10") in order to control the crack width and spacing.
  2. A min. of 0.24% shall be used for the roof slabs since it is subjected to higher temperature. Variations than the floor slabs. This is required to take care of temperature differences.
  3. It is advisable to not to use 6mm bars as main bars as this size available in the local market is of inferior not only with respect to size but also the quality since like TATA and SAIL are not producing this size of bar.

BEAMS

ACI reinforcement detailing in cantilever beam:

  1. A min. of 0.2% is to be provided for the compression bars in order to take care of the deflection.
  2. The stirrups shall be min. size of 8mm in the case of lateral load resistance
  3. The hooks shall be bent to 135 degree.

Details of Grid beams
Details of Main & Secondary beams

 

Search AboutCivil

Related Civil-Engg. Content