Activity Relationships in Primavera
There are four kinds of relationships:
Start to Start:
When both the activities start at the same time (Simultaneously), the relationship between them is said to be SS relationship.
Start to Finish:
When predecessor starts, successor will end. This is called SF relationship.
Finish to Start:
When predecessor ends, successor will start. Means one activty finishes to pave way for an other, to get started. This is called FS relationship.
Finish to Finish:
When both the activities finish at the same time (Simultaneously), the relationship between them is said to be FF relationship.
Download 7 Primavera Project Planner Video 7 - Calendars & Holidays
Primavera Project Planner P3 Video 8 - Relationships, adjusting Project Schedule, Tutorial |
|
Click here to Download |
Download 9 Primavera Project Planner Video 9 - Filtering activities and Progress Reporting
More Coming Soon
Be the FIRST to know about new Video Tutorials....
Fields maked with * are required
Related Subscription Lists: Newsletter | Video Lectures |