Definition

Chain survey is the simplest method of surveying. In this survey only measurements are taken in the field, and the rest work, such as plotting calculation etc. are done in the office. This is most suitable adapted to small plane areas with very few details. If carefully done, it gives quite accurate results. The necessary requirements for field work are chain, tape, ranging rod, arrows and sometime cross staff.

  • It is a system of surveying in which sides of various triangles are measured directly in the field and NO angular measurements are taken.
  • It is the simplest kind of Surveying
  • It is adopted when Level of accuracy required is not high

A Chain survey may be executed in the following steps:

1. Reconnaissance

The preliminary inspection of the area to be surveyed is called reconnaissance. The surveyor inspects the area to be surveyed, survey or prepares index sketch or key plan. Walk the whole area and thoroughly examine the ground, note the position of boundaries, road, and river etc., various difficulties to chain lines, select stations, and prepare neat sketches called index sketches or key plan.

2. Marking stations

Stations are marked with ranging rod, or wooden peg, driving a nail or spikes if hard surface, or embedding stone with a cross mark.

3. Reference sketches

After marking the station should be referenced i.e. located by measurement called ties taken from 3 permanent points which are easily identified such as corner of building.

4. Running survey line

After the preliminary work, chaining is started from base line and carried throughout all the line of the framework continuously. So chain is laid and kept lying, offset are taken to locate the nearby details. Make ranging wherever necessary. Measure the change and offset and enter in the field book.

Chain Survey is Suitable when

  1. Ground is fairly level and simple
  2. Plans are required on large scale e.g. fields
  3. When area is small in extent

Chain Surveying is Not Suitable

  1. For Large Areas
  2. When too many details are required
  3. Wooded countries
  4. Undulating areas
  • Since the triangle is a simple plane geometrical figure, it can be plotted from the measured length of its sides alone; therefore, the principle of chain survey is Triangulation.
  • In chain surveying, a NETWORK of TRIANGLES is preferred.
  • Preferably all the sides of a triangle should be nearly equal having each angle nearly 60 to ensure minimum distortion due to errors in measurement of sides and plotting.
  • Generally such an ideal condition is not practical always. Usually attempt should be made to have WELL CONDITIONED TRIANGLES in which no angle is smaller than 30 and no angle is greater than 120.

Area by Chain TriangulationProcedure for Measurement of an Area by Chain Triangulation

PROCEDURE:

  • Let ABCDE be the given field whose area is to be measured, fix the pegs at A, B, C, D & E.

  • Divide area into three triangles ADE, ABD and BCD by joining AD and BD.

  • Measure the lengths AB, BC , CD, DE, EA, AD and BD.

  • Calculate the area of the triangles.

  • The sum of the areas of the three triangles is the area of the given field.

sum of the areas of the three triangles

sum of the areas of the three triangles

RESULT:

The area of the given field = _______

Survey Station:

Survey stations are of two kinds:

  1. Main Stations
  2. Subsidiary or tie

    Main Stations:

Main stations are the end of the lines, which command the boundaries of the survey, and the lines joining the main stations re called the main survey line or the chain lines.

Subsidiary or the tie stations:

Subsidiary or the tie stations are the point selected on the main survey lines, where it is necessary to locate the interior detail such as fences, hedges, building etc.

Tie or subsidiary lines:

A tie line joints two fixed points on the main survey lines. It helps to checking the accuracy of surveying and to locate the interior details. The position of each tie line should be close to some features, such as paths, building etc.

Base Lines:

It is main and longest line, which passes approximately through the center of the field. All the other measurements to show the details of the work are taken with respect of this line.

Check Line:

A check line also termed as a proof line is a line joining the apex of a triangle to some fixed points on any two sides of a triangle. A check line is measured to check the accuracy of the framework. The length of a check line, as measured on the ground should agree with its length on the plan.

Offsets:

These are the lateral measurements from the base line to fix the positions of the different objects of the work with respect to base line. These are generally set at right angle offsets. It can also be drawn with the help of a tape. There are two kinds of offsets:

  1. Perpendicular offsets
  2. Oblique offsets

The measurements are taken at right angle to the survey line called perpendicular or right angled offsets. The measurements which are not made at right angles to the survey line are called oblique offsets or tie line offsets.